CONSTRUCTION STAGE |
PROGRESS |
COMMENT |
|
Base concrete |
Poured |
|
|
First stage: Setting out of reinforcement |
Done |
|
|
Second stage: Concrete pouring |
Done |
|
|
Setting out of reinforcement: (up-right |
Done |
|
|
Casting & shuttering of stub columns |
Work in progress |
Rain interruption |
|
SERVICES |
CHARGES |
COMMENT |
|
Structural Plans - More plans needed |
$3,000 if one off payment $14,000 if installments |
No funds to pay for this and request immediate assistance |
|
Labour |
USD8,000 |
Paid only USD4,620.00 Urgently need balance |
|
Plant and Machinery |
Initial request of USD3,500.00 |
Requesting funds to pay for this urgent service |
|
Steel fixing |
USD550.00 |
Paid |
|
Soil Testing |
USD480.00 |
Paid |
|
|
|
|
Raw Material Consumption So Far: - 290 bags of cement; - 60cubic meters of stones; - 65 cubic meters of river sand
Head Office Project Outline and Purpose click : http://www.ccaphresynod.com/headofficeproject.htm
MEMBER AND WELL WISHERS CALL
We are now out of funds. We had to borrow some to enable the Contractor to reach the 'casting & shuttering of stub columns' Stage; as it is not advisable to leave the reinforcement steel as they are.
Rainy season began and we kindly request you, to do all you can - through God’s grace, to support this crucial level of the project. Blessed is the Hand that gives, so be assured that the Lord will reward you for your service to His kingdom. Call us or e-mail us at our contact details and offer your kind assistance. Keep the prayers going as we continue to see The HAND OF GOD in this project.
Thank You.